Cogeneration power plant


rompetrol render crop

On August 19, 2020, the Kazakh-Romanian Energy Investment Fund signed an EPC (Engineering, Procurement and Construction) contract with Calik Enerji (Turkey) for the turnkey construction of the cogeneration plant on the Petromidia platform. The total investment in this project amounts to about 148 million USD, generating about 11 million  USD annually in taxes paid to the state budget each year.
 

The construction of the cogeneration plant began in May 2021 and the deadline for commissioning the new plant is the end of July 2023.

Rompetrol Energy is the company that ensures the implementation of the project “construction and operation of Cogeneration Thermal Power Plant”.

The new unit will comply with the highest technological standards of energy efficiency and environmental protection, and will be built in partnership with the Midia Thermal Power Plant - currently owned by the Ministry of Energy (56.58%) and KMG International (43.42%) .

Midia S.A. Thermal Power Plant transferred to Rompetrol Energy SA the necessary assets to carry out the activity of production of thermal energy and demineralized water, the related service of connection and distribution of electricity and legal documents related to the continuation of the activity and implicitly the employees involved in the assigned activity.

Status of works Q 4, 2022

 

Building Permit for the Power plant - COMPLETED;

Construction permits for the natural gas pipeline: obtained from Corbu and Năvodari City Halls in October 2022;

Detail design: the elaboration of the technical execution documentation for the whole project is at an advanced stage (90%);

ATR: obtained in June 2022,and ATR for the natural gas was obtained at the end of 2021;

Procurement: at an advanced stage (92%); Main equipment delivered: GT1 and GT2 gas turbines, GSUT1 and GSUT2 large transformers including all electrical equipment; Estimation of complete delivery of equipment needed for the project – March 2023;

Construction works: at an advanced stage (47%); all foundations and buildings have been completed; work is being done on estacades, the underground pipeline network, the gas pipeline as well as equipment installation works;

 

Check below the videos